Landslip overlays on the Mornington Peninsula
Landslip overlays on the Mornington Peninsula decide whether a retaining wall needs a planning permit as well as a building permit. This page collects the Shire and Frankston controls that were on the public record in November 2026. Check the lot before you rely on it. Overlays change.
Does this wall need a permit?
This follows the Victorian rules and the two local councils, checked November 2026. It says “likely”. A building surveyor decides. It is general information, not legal advice.
Is the wall less than 1 metre high?
Yes, under 1 metre
Is it only a garden wall, not part of other building work, and not protecting the neighbour’s land?
Likely exempt from a building permit under Schedule 3 item 15 [1]. It must still meet the building code. An erosion overlay can still need a planning permit.
No. It is part of a deck, driveway, pool or extension, or it holds the neighbour’s land.
Likely needs a building permit even under 1 metre [1]. Check with a building surveyor.
No. It is 1 metre or taller
A wall of 1.0 m is not in the “less than 1 m” exemption [1].
- Mornington Peninsula Shire. The Shire does not issue building permits. A private building surveyor does. Penalties for work without a permit can exceed A$80,000 [3].
- Frankston. You can use the municipal surveyor or a private one. Boundary work often needs a Protection Work Notice. The checklist asks for footings in natural ground of at least 100 kPa, not fill [4] [5].
Likely a building permit, and a planning permit first if an overlay applies. Check with a building surveyor.
McCrae, January 2025
The Board of Inquiry found that a burst South East Water main, about 450 m south of 3 Penny Lane, leaked undetected for months, about 40.3 million litres, and caused the 5 January 2025 landslide and the later McCrae landslide [7][8]. The lesson for a house wall is practical: a leak above a slope is not a plumbing footnote.
EMO1 to EMO6, already on the Shire map
The Shire’s landslide page sets out earlier overlays. EMO1 and EMO2 cover hinterland from Arthurs Seat south to Cape Schanck and Flinders. EMO3 is around Ballar Creek at Mount Eliza. EMO4 and EMO5 are around Tanti Creek at Mornington and parts of Flinders. EMO6 follows the Western Port coast from Somerville toward Cape Schanck [9].
EMO7, from 6 January 2026
Amendment C312morn put an interim erosion management overlay on about 33,000 properties rated highly susceptible to landslide, in effect from 6 January 2026. The Shire later announced, on 19 October 2026, a further amendment aimed at cutting that interim area, using LiDAR and field inspections in McCrae, Red Hill, Rye, Blairgowrie, Mount Eliza, Mount Martha and Portsea [9]. Permanent controls were described as years away. Because that second amendment was still moving when this page was written, use the Shire EMO map for the lot in front of you, not this paragraph alone.
In an erosion overlay, works can need a planning permit and a geotechnical report [9]. The map is on the Shire site.
Frankston’s EMO1 is Olivers Hill
Frankston’s schedule describes historically documented slope instability since the 1870s, from the Olivers Hill slips to Kackeraboite Creek. A retaining wall is exempt there only if it does not exceed 1 m, is not associated with other building work, and does not provide landslip protection to adjoining land. Cut or fill over 0.6 m can trigger a permit, and applications need a geotechnical assessment [10].
FAQ
Does EMO7 replace the building permit?
No. It is a planning overlay. The building permit, where one is required, is a separate step, and on the Peninsula a private surveyor issues it [3].
What did the Mount Martha Esplanade project show?
The Shire’s landslide repair there uses two bored-pile retaining walls taken through granite, with completion scheduled for December 2026 [16]. That is a public works contract, not a house quote.
Sources (6), checked Nov 2026
- McCrae Landslide Board of Inquiry, report
- ABC News, McCrae landslide inquiry findings, 9 Oct 2025
- Mornington Peninsula Shire, Landslide susceptibility
- Frankston Planning Scheme, clause 44.01 schedule 1 (EMO1, Olivers Hill)
- Mornington Peninsula Shire, Building permits
- Mornington Peninsula Shire, Mount Martha landslide reparation, Esplanade